NATIONAL OPEN UNIVERSITY OF NIGERIA
UNIVERSITY VILLAGE, PLOT 91, CASDASTRAL ZONE, NNAMDI AZIKIWE EXPRESS WAY, JABI, ABUJA.
FACULTY OF MANAGEMENT SCIENCES
JANUARY 2018 EXAMINATION
COURSE CODE: BFN 409
CREDIT UNIT: 3
COURSE TITLE: PROJECT EVALUATION
TIME ALLOWED: 3 HOURS
Instructions: 1. Attempt question number One (1) and any other Two (3) questions.
2. Question number 1 carries 25 marks, while the other questions carry 15
3. Present your work in coherent and orderly manner.
QUESTION ONE (COMPULSORY)
Calculate the net present value of a project which cost N500,000 but generates cash inflows of N150,000, N300,000, N400,000, N200,500, and N192,500 over a five year period. The required rate of return is 10%. These discount factors are relevant: 0.909; 0.826; 0.751; 0.687; and 0.594 respectively.
(b) Compare Financial Analysis with Economic Analysis in relation to project evaluation.
QUESTION TWO
(a) Figures below represent some aspects of a project cost.
Land, Building and steel structure =N= 22,000,000
Machinery and equipment -----
Storage tanks 8,100,000
Utilities -----
Pre-operational expenses 1,450,000